In the previous article we showed how we performed the preparation of reforms restaurants copopren then place the sheet, this time we are placing the sheets.
We started
Post the copopren 150-20, then over the sheet of Polyethylene on copopren a look this process is finished we have to place the mesh. At the end of this whole process of the sheets and mesh it is the turn to concrete.
The H250A poured concrete pump after discharge vibrant rule is passed during the hardening process of concrete troweling helicopter is made.
Such reforms restaurants are one of the reforms that we carry out reforms of our customers.